The Cooperage: Roof Replacement & Lead Work
|
Contract: The Cooperage, Tower Bridge Piazza, London SE1
Client: Ashley Management
Value: £210,000
Programme: 16 weeks
We replaced the main roof, consisting of approximately 18,000 slates, without the use of a temporary scaffold roof to save our client cost and time.
Works were completed to a tight 16 week programme and we maintained a leak free environment for residents during the removal of the original roof covering.
The roof was replaced using a natural Spanish slate, a new asphalt roof was also installed and associated lead works completed. The insulation was upgraded to comply with current building regulations. |
|
|
Works:
- Slate & asphalt roof replacement
- Lead works
|
|
|
|
|